OC2003-406
2003-08-01
Mines and Energy
Electrical Power Control Act, 1994
Under the authority of section 5.1 of the Electrical Power Control Act, 1994, the Lieutenant Governor in Council is pleased to direct the Board of Commissioners of Public Utilities to:
i) adopt a policy that a utility’s costs, relative to projects exempted from the Public Utilities Act and the Electrical Power Control Act, 1994 by Order in Council, shall be recovered fully in appropriate rates, unless otherwise directed on a specified project; and,
ii) that costs related to the Lower Churchill Development Project will be excluded from such policy directive.