Under the authority of section 5.1 of the Electrical Power Control Act, 1994, the Lieutenant Governor in Council is pleased to direct the Board of Commissioners of Public Utilities that:

1) Effective July 1, 2013, Island industrial customer rates will no longer be frozen. Effective on this date rate increases for island industrial customers will be phased in over a three year period, with funding for this phase-in to be drawn from the January 1, 2007 to June 30, 2013 accumulated Load Variation (the Rate Stabilization Plan Surplus) component of the Rate Stabilization Plan and credited to the Island industrial customer Rate Stabilization Plan effective June 30, 2013;

2) On June 30, 2013 the Island industrial customers' Rate Stabilization Plan will be credited with $56.5 million, the estimated Rate Stabilization Plan amount required to phase-in industrial customer rates, based on Newfoundland and Labrador Hydro's General Rate Application. The remaining balance in the Rate Stabilization Plan Surplus on June 30, 2013, will be transferred to the credit of Newfoundland Power's Rate Stabilization Plan. No future adjustments will be made to these amounts credited. Effective July 1, 2013 all Island industrial customers, with the exception of Teck Resources, will be subject to the same standard industrial rate, equivalent to the existing base rate but excluding the Rate Stabilization Plan adjustment currently in place;

3) Teck Resources rate increase will be phased in, to a reasonable degree, in three equal annual percentage increases, and at the end of the phase-in period Teck Resources will be subject to the standard industrial rate;

4) Over the three year Island industrial rate phase in period, the shortfall in Newfoundland and Labrador Hydro's revenues when compared to revenue at the Board of Commissioners of Public Utilities-approved Island industrial customer rates, shall be funded from the Island industrial customer Rate Stabilization Plan;

5) Notwithstanding Items 1) through 4) above, effective January 1, 2014, the Island industrial customers will be subject to Rate Stabilization Plan rate changes in accordance with the Board of Commissioners of Public Utilities-approved methodology;

6) Newfoundland and Labrador Hydro's General Rate Application process shall include a Rate Stabilization Plan surplus refund plan to ratepayers. The refund plan shall comprise direct payments or rebates to ratepayers and shall not be in the form of an electricity rate adjustment. This refund plan will exclude Island industrial customers who will receive Rate Stabilization Plan surplus funds through the three year phase-in of new rates. The Board of Commissioners of Public Utilities shall make the final determination on the details of the refund to remaining ratepayers;

7) Newfoundland Power's portion of the Rate Stabilization Plan Surplus shall be distributed as a direct payment or rebate to its ratepayers and shall not be in the form of an electricity rate adjustment; and

8) Newfoundland and Labrador Hydro's General Rate Application shall be based on a 2013 test year in the determination of new electricity rates for customers.

(OC2013-089 revoked item 8)